Performance of Orkney vessels for marine renewable operations: waves, currents and ship motion

2014
31 January 2014 by
Performance of Orkney vessels for marine renewable operations: waves, currents and ship motion
Client logo: Aquatera (EMEC)

Client

Aquatera (EMEC)

Date

2014

Location

EMEC test sites, Orkney, Scotland

Budget

c. €35k

Needs

Installing, maintaining and recovering wave and tidal devices depends on vessels working in strong currents and narrow weather windows, which drives cost and risk for the sector. EMEC, with Scottish Government funding, set up a coordinated programme of vessel and maritime technology trials in Orkney. It needed reliable measurements of the conditions and of vessel and mooring behaviour to assess what local vessels can achieve safely.

Objectives

01

Measure currents and waves during each vessel trial

02

Record vessel position, heading and motion, and mooring line loads, with high accuracy

03

Relate vessel and mooring behaviour to metocean conditions to support operational limits

Missions

01 Instrumentation of Orkney workboats and a barge with a POS MV motion and positioning system
02 Current and wave measurements with vessel-mounted and seabed ADCPs at the trial sites
03 Measurement of mooring line loads during position-keeping and underslung-load trials
04 RTK post-processing of positioning data and analysis of each trial against the measured conditions
05 Delivery of trial reports to the programme

Resources deployed

Applanix POS MV motion and positioning system, post-processed with POSPac (RTK)

ADCPs mounted on the vessels looking down, and on seabed frames

Load cells on mooring lines

Orkney workboats and a barge, trials at Fall of Warness, Clestrain Sound and Shapinsay Sound

Preparing the seabed frame and buoys for a position-keeping trial

Preparing the seabed frame and buoys for a position-keeping trial

Deploying an ADCP from a workboat at the trial site

Deploying an ADCP from a workboat at the trial site

Workboat towing a barge during the vessel trials

Workboat towing a barge during the vessel trials

Results

7 cm

horizontal position accuracy after RTK post-processing

0.5 m

position-keeping precision of the moored barge

2.2 m/s

peak current during moored workboat trials

  • Synchronised records of current, vessel motion and mooring loads for each trial manoeuvre
  • Moored barge held position to about 0.5 m, with about 1 m repeatability between patterns
  • Four-line mooring gave tighter position keeping than three lines for the workboat trials
  • Load measurements gave crews a practical understanding of mooring loads and how they vary in swell
  • Objective basis for defining operational limits and planning offshore operations in the sector